How long does it take to finish a basement?
Most Roots Finished Basements projects take 7 to 8 weeks from the day the permit is issued to the final walkthrough. The permit itself sits in front of that and depends on the city, usually one to three weeks in south Utah County. A homeowner who signs today is typically living in a finished basement about two and a half months from now.
Below is the week by week shape of a typical 1,200 square foot basement with two bedrooms and a bathroom, what the homeowner has to decide and when, and the handful of things that actually cause delays.
5.0 on Google from 30 reviews
Every review is shown in full on the reviews page and on Google. These are the three most recent.
Noah and crew are great to work with. They are building something great at Roots! From quality work to great design ideas, they can do it all. I would definitely trust them with something as important as home renovation!
KILLER TEAM!!! CLEAR AND CONCISE COMMUNICATION! I loved chatting with Noah, Smart guy and we got along very well! Can’t wait to work with them on my Next Project! I will Definitely be using them for sure! GO SEE NOAH!
(Translated by Google) 100% recommended. Excellent service, very attentive, and responds quickly to any questions. I wholeheartedly recommend them. (Original) 100% recomendable excelente atención y muy atento y responde rápido cualquiera duda ciegamente lo recomiendo totalmente
Before the clock starts
The site visit, the written proposal and the signed agreement happen before the permit is filed. Roots draws the layout around the builder's rough ins, the homeowner approves it, and the plans go to the city. Material selections for cabinets, tile and flooring are due during the permit wait so nothing is ordered late.
Week by week
| Week | What happens | What the homeowner does |
|---|---|---|
| 1 | Layout marked on the slab, framing of walls, soffits around ductwork and beams, egress window wells cut and set. | Walk the framed rooms. This is the last cheap moment to move a wall. |
| 2 | Plumbing rough in on the builder's stubs, HVAC runs to every room, electrical rough in for lights, outlets and dedicated circuits. | Confirm light and outlet locations on the walk through. |
| 3 | Four way inspection by the city covering framing, plumbing, electrical and HVAC. Corrections if any. Insulation. | Nothing. The inspection is scheduled by Roots. |
| 4 | Drywall hung, taped and textured. The basement goes from studs to rooms in a few days. | Final paint color decision if not already made. |
| 5 | Prime and paint. Doors and trim. | Confirm cabinet and vanity delivery dates with the schedule. |
| 6 | Cabinets, vanities, closet systems. Tile in the bathroom. | Nothing beyond selections already made. |
| 7 | Flooring, carpet and luxury vinyl plank. Electrical finish, plumbing finish, HVAC finish. City final inspection, punch list walked with the homeowner, cleanup. | Walk the space, then sign off on the punch list. |
| 8 | Used on larger basements, second bathrooms, kitchenettes, theaters, and when an inspection correction or a back ordered item pushes a trade back a few days. | Friday updates say where the schedule stands. |
The company's own contract goal is to finish inside seven weeks of working days, and larger scopes use the eighth week. The schedule is built backwards from a real finish date before the first day, with every inspection and material lead time on it, and the homeowner gets a scheduled update every Friday whether or not there is news.
What causes delays, honestly
- Permit wait. Set by the city, not the contractor. One to three weeks is typical in Salem, Spanish Fork, Payson and Santaquin. The clock on the 7 to 8 weeks starts when the permit is issued.
- Late selections. Tile, cabinets and flooring have lead times. A selection made in week four lands in week six or seven. Roots asks for selections during the permit wait for this reason.
- Inspection corrections. A failed item at the four way inspection means a fix and a reinspection. Roots schedules the correction into the same week when the city can come back.
- Change orders. Every change is priced in writing within 48 business hours and signed before the work starts. An approved change extends the completion date by the time it reasonably takes.
- Back orders. A window, a vanity or a tub that ships late. The schedule works around it where it can and the Friday update says so.
- Access. Crews work roughly 7 a.m. to 6 p.m., Monday through Saturday. A basement that is not accessible on a scheduled day costs that day.
Why is my basement taking so long is the second most common timeline search after how long it takes. The usual answers are a permit that was never pulled, a contractor running too many jobs at once, or changes made mid stream without a schedule reset. A fixed finish date in the contract, a Friday update and a written change order process are the three things that prevent it.
When to start after closing on a new home
There is no need to wait for the house to settle before finishing a basement in a new build; the foundation has cured and the builder's warranty on the structure continues. Finishing the basement generally does not void a builder warranty, though the builder will not warrant the finished work itself, and the homeowner should confirm any specific builder policy. Plenty of Roots customers start within the first few months of moving in, often after the yard is done.
Can a basement be finished in winter?
Yes. A basement finish is indoor work. Egress window cuts are the only outdoor step and they are done in a day. Winter is in fact a good season for it, since the crew is not competing with outdoor projects.
Questions people ask
How long does it take to finish a basement?
Most Roots Finished Basements projects take 7 to 8 weeks from permit to final walkthrough. The permit wait in front of that is usually one to three weeks depending on the city. Larger basements with a kitchenette or a second bathroom use the full eight.
How long does the permit take?
It depends on the city. One to three weeks is typical in Salem, Spanish Fork, Payson and Santaquin. Roots submits the plans and schedules the inspections. The 7 to 8 week build clock starts when the permit is issued.
What does the homeowner have to decide, and when?
The layout before the permit is filed, then cabinets, tile, flooring and paint during the permit wait, then light and outlet locations at the framing walk through. After week two the decisions are made and the homeowner mostly watches it come together.
Can you finish a basement in 6 weeks?
A small, simple basement can come in under seven weeks, but Roots schedules to 7 to 8 so the finish date in the contract is one it can hit. A date that is promised short and missed costs the homeowner more than a date that is set honestly.
Call 435.677.6050 to ask for a square foot estimate on your basement. The number comes in writing before anything starts.
Call 435.677.6050